Relocation Of Maintenance Workshop

Completed the relocation of the workshop for Goodman Fielder Moorebank

  • Isolate DB11 DB11A DB11B and DB14A and make safe for demolition works.
  • Install temporary DB’s in old crumb plant and old maintenance store.
  • Pull back submains from DB11 and extend to new position install marshalling panel to extend cables.
  • Supply and install all associated cable tray and unistrut as required
  • Supply and install 56C520 twenty amp outlets as per CAD drawing.
  • Supply and install 56C310 ten amp outlets as per CAD drawing.
  • Supply and install 56C310 ten amp pendant outlets as per CAD drawing.
  • Supply and install Cat6 jacks as per CAD drawing.
  • Supply and install 56C520RC twenty amp RCD outlets as per CAD drawing.
  • Supply and install 15amp GPO as per CAD drawing.
  • Supply and install 20amp GPO as per CAD drawing.
  • Supply and install 10amp GPO’s as per CAD drawing.
  • Connect hot water heaters supplied by others.